  • Lapping is not allowed for the bars having diameters more than 36 mm.
  • Chair spacing maximum spacing is 1.00 m (or) 1 No per 1m2.
  • For dowels rod minimum of 12 mm diameter should be used.
  • Chairs minimum of 12 mm diameter bars to be used.
  • Longitudinal reinforcement not less than 0.8% and more than 6% of gross C/S.
  • Minimum bars for square column is 4 No’s and 6 No’s for circular column.
  • Main bars in the slabs shall not be less than 8 mm (HYSD) or 10 mm (Plain bars) and the distributors not less than 8 mm and not more than 1/8 of slab thickness.
  • Minimum thickness of slab is 125 mm.
  • Dimension tolerance for cubes + 2 mm.
  • Free fall of concrete is allowed maximum to 1.50m.
  • Lap slices not be used for bar larger than 36 mm.
  • Water absorption of bricks should not be more than 15 %.
  • PH value of the water should not be less than 6.
  • Compressive strength of Bricks is 3.5 N / mm2.
  • In steel reinforcement binding wire required is 8 kg per MT.
  • In soil filling as per IS code, 3 samples should be taken for core cutting test for every 100m2.

100622-A-4015L-019